NL EN

Do you also mount climate ceilings higher than 5 meters?

With raised mobile scaffolding we mount ceilings up to a height of 5 meters. Fixed scaffolding must be erected above this. The latter is a labor-intensive process that must be taken into account in both the costs of the project and the planning. In addition, it must be taken into account that the release of the climate ceiling decreases as it is mounted at a higher height. At a height of 5 meters there is a correction factor of approx. 0.90 and for heating with no less than 0.65 compared to the standard power at ceiling height of 2.7 m.